City Road Construction Update 7/19/23

Posted Wednesday, July 19, 2023
Updates

The Crescent Connector Project and the Brickyard Culvert Replacement Project are on hold at this time. The contractor has been called off both sites to provide emergency assistance resulting from the floods. We anticipate the Crescent Connector Project contractors may be off-site for two additional weeks, and the Brickyard Culver Replacement Project contractors may be off-site until July 24, 2023. 

All the businesses at 34 Park are operating under their normal hours of operation. Off-street parking for businesses at 34 Park Street is available by entering the driveway at the south end of the building and following the directional signs posted there.

The Main Street Waterline Replacement Project contractors continue to work on this project and have yet to be asked to help with emergency assistance. 

Residents or businesses can view updates on these projects on the City's road construction webpage at www.essexjunction.org/news/city-road-construction.